Highway construction continues moving along across the region.
On Highway 11 between Roseau and Warroad, paving is complete on the east half. Crews will now work on slopes and ditches, while culvert replacements continue on the west-half detour. The airport realignment is about halfway complete, with the project still on schedule for a September finish.
In Greenbush, Stage One paving has wrapped up. Stage Two closed Highway 11 between Seventh and Fourth Streets for about seven weeks.
And at the Warroad bridge, both piers are complete and crews have begun setting new beams. That project is ahead of schedule and expected to finish in November.
For more information and current traffic impacts, visit mndot.gov.